Lesson 12
Measures and payback
The audit of lessons 10 and 11 found what the plant wastes. This lesson turns the findings into a plan: a copy of the network as it will be, the measures made in it one by one, the two versions side by side — and, from the difference, what each measure pays back.
Scenarios: one file, several networks
A scheme file can hold several versions of the same network. The first one is the baseline — the plant as it is. The others are copies you change: the plant as it will be. A measure is never applied to the baseline, so the audit of the real plant always stays in the file.
| Each scenario has its own | All scenarios share |
|---|---|
| elements, connections, card rows, cyclograms, texts and zones | Input parameters (hours, prices), units, thresholds, the Design / Audit mode |
So the comparison is between networks under the same tariffs and hours.
-
Start from the audit of lesson 11
Open
lesson11.gf9, save it at once aslesson12.gf9and press Audit — the measures are searched only by the button. Check COMP against lesson 11:Row, COMP Expected Unit Audit pressure 6.5 bar Audit power 8.7 kW Qn average 995.68 NL/min Min audit pressure 6.1832 bar Power calibration 0.752 Annual cost calibrated 2172 € PG reads 6.35 bar, FM 1966 NL/min: both within accuracy. If PG still reads 6.0 from the experiment of lesson 11, set it back first.
-
Read the measures at the measured energy
Open the Problems panel and click the green Recommendations counter. The measures of lesson 10 are there again, with the leaks of lesson 11 — but every figure in euros is now multiplied by Power calibration 0.752: the money is counted at the energy the meter measured, not at the price of air of Input parameters.
Problem On Value Leakage is above the target: a repair programme pays back (25 % of the average demand, 249.3 NL/min; target 5 %) COMP 458 €/yr The compressor setting can be lowered (6.5 bar → 6.183 bar without a pressure deficit at maximum load) COMP 154 €/yr [-] 2 × TUBE_BLOWING — the consumer gets more pressure than it needs and uses more air B2, B1 209 €/yr 6.462 bar instead of 4 bar; 188.6 NL/min instead of 126.4 at average load B2 136 €/yr 6.45 bar instead of 6 bar; 557.8 NL/min instead of 524.1 at average load B1 73 €/yr Undersized pipe: high air velocity and pressure loss (9.56 m/s and 414 Pa/m at maximum load; limits 9 m/s and 200 Pa/m) T1 0.015 bar The compressor runs at a low average load (average 39.8 % and peak 78.4 % of the capacity 2500 NL/min) COMP The rows name the elements by ID and card label: COMP is ID7 compressor, B1 and B2 are ID1 and ID2, T1 is ID3 D-1 IN_EQUAL TEE.
Select a row and look at the Apply button on the bottom bar. It is enabled only for a measure that knows exactly what to change in the scheme:
Can be applied What Apply changes The compressor setting can be lowered Audit pressure := Min audit pressure, rounded up to 0.01 in the unit of the row Undersized pipe, This pipe limits the setting the pipe (or tee) is replaced by the catalog size the measure names — only when that size meets the limits Condensate drain loses compressed air the drain becomes an electronic zero-loss one Select Undersized pipe of T1: Apply is enabled, and the detail panel names the tee it would put in — d-1.5 in_Equal Tee (37.5 mm), 3.6 m/s and 44 Pa/m. Leave it for now; the last item of Try this next applies it. A regulator before a consumer, a leak repair, another compressor control — these you make by hand in a scenario, as the next steps do.
The measures at the measured energy; the selected one can be applied. -
Make a copy of the plant for the plan
Choose Scenario → New from current.... The program offers the name
Proposed; press OK. The copy becomes the current scenario:- a strip above the sheet reads SCENARIO: Proposed (the baseline reads BASELINE: As is, in orange); a click on it lists the scenarios;
- the window title ends with — Proposed.
Why not press Apply on the lower setting straight away? Pressed in the baseline, Apply makes this copy by itself. But the lowest setting depends on the network: B2 takes 6.46 bar where 4 would do, and every litre it blows runs through P1 and takes pressure from B1. Put the regulator in first, and the setting can go lower. Make the measures that change the network first, the setting last.
-
Put a regulator before B2
The regulator before B2 is a measure the program cannot apply: it means a new element on the sheet. Make sure you are in Proposed, then do what lesson 8 did: release the connection P3 → B2, place a regulator from Regulators — MD1-R00-1/8 — between them, join both sides and rename it
R2(F2). Set:Item Row Value R2 Pout 4 bar from the list; what Audit required pressure of B2 asks for Pout of a catalog regulator offers only the set points at which the maker measured its flow curves — the list of the card. The knob of a real regulator turns smoothly; for a setting between the curves there is Audit set point: any number, computed on the nearest curve. Leave it empty for now.
Press Audit and click R2. A regulator does not give exactly its set point: its outlet droops with the flow along the curve of the card, and this one also needs at least 1 bar across it (dPmin).
Row, R2 Value Unit m 0.0083 kg/s Pin 6.3765 bar well above 4 + 1 Pout actual 3.9786 bar 0.02 bar below the set point: the droop delta P 2.3979 bar the pressure the regulator takes away on purpose Qn 419.374 NL/min what B2 now blows while it runs Opening 33.5935 % Required set point 4.0214 bar what gives B2 its 4 bar The regulator droops a little below its set point; Required set point says how much to set. A 1/8 in regulator at a third of its opening droops very little — but enough: B2 gets 3.9786 bar, 0.0214 short of its required 4, and shows Pressure deficit 0.0214 bar. While a consumer is short, no setting of the compressor cures it — the regulator holds its own outlet — so the list has no The compressor setting can be lowered now. Required set point is the answer: keep Pout at 4, type
4.03into Audit set point of R2 — the estimate rounded up — and press Audit again. The droop of the curve moves with the set point:Row Value Unit R2, Pout actual 4.006 bar what B2 gets R2, Set point vs design 0.03 bar Audit set point − Pout of the card B2, Pressure margin 0.0062 bar the deficit is gone B2, Qn artificial demand 0.75 NL/min what the 6 mbar of margin costs B2 blows about 420 NL/min while it runs instead of about 610. Less air runs through P1 at maximum load, B1 gets more pressure, and The compressor setting can be lowered is back in the list — now from 6.5 bar to about 6.16 bar, lower than the 6.183 of the baseline.
-
Apply the lower setting
Select The compressor setting can be lowered and press Apply. Proposed is not the baseline, so the change goes into it: Audit pressure of COMP becomes 6.17 bar — the minimum rounded up, so that the setting never ends below the one found. The program runs the audit again and reopens the Problems panel with a fresh list; the measure is gone from it, and the change is written into the journal of measures of Proposed — step 7 shows where to read it.
Row, COMP As is Proposed Unit Audit pressure 6.5 6.17 bar Qn 1960.35 1708.22 NL/min Load at maximum 78.41 68.33 % Qn leak total 247.39 236.904 NL/min Qn average 995.68 899.037 NL/min Cs 2889 2528 € Power calibration 0.752 0.752 Annual cost calibrated 2172 1900 € Leak share 25.04 26.52 % Leak cost 544 504 € Min audit pressure 6.1832 6.1613 bar Power calibration in Proposed is not measured again: the meter measured the plant as it is. Its note reads From the baseline scenario — every scenario is priced at the energy the baseline measured, so the scenarios can be compared at all.
Check by hand: the cost of the plan
Without a machine the cost is the price of air corrected for the pressure: 0.024 €/Nm³ × (p / 6)0.603 × Qn average × 1920 h, then × 0.752. As is: (6.5 / 6)0.603 = 1.0495, 995.68 NL/min → 2889 € → 2172 €. Proposed: (6.17 / 6)0.603 = 1.0170, 899.04 NL/min → 2528 € → 1900 €. The regulator and the lower setting together save 272 € a year.
The plan after the regulator and the lower setting: the strip above the sheet says which scenario you are in. PG and FM now carry warning signs. Their readings, 6.35 bar and 1966 NL/min, were taken on the plant as it is; in Proposed the setting is lower and B2 takes less, so the model no longer matches them: PG shows Pressure deviation 0.28 bar (the model gives 6.07), FM Qn deviation about 258 NL/min. A reading belongs to the network it was taken on. Leave the two rows as they are: the comparison counts them as two warnings of Proposed, and step 7 shows where. Clearing Audit measured of PG and FM in Proposed removes the signs — the baseline keeps its readings either way.
-
Model the leak repair in a scenario of its own
The biggest measure is the leaks, and it has two prices: a survey and the repairs. Keep it apart so that its payback can be seen on its own. With Proposed current — the regulator in place, the setting at 6.17 — choose Scenario → New from current... and name the copy
Leaks repaired.A repair cannot be applied by the program: you tell the audit what the leak test will show after it. Say the survey brings the leaks down to a third. On COMP:
Row As is Leaks repaired Audit leak t load 6 s 2 s loaded Audit leak t unload 54 s 58 s unloaded Audit leak test pressure 6.5 bar 6.5 bar copied — leave it Press Audit. The test gives 2500 × 2 / 60 = 83.3 NL/min at 6.5 bar; at the lower network pressure of 6.17 bar the leaks are a little less, 79.03 NL/min — a third of the 236.9 of Proposed.
Row, COMP Expected Unit Qn leak at test 83.33 NL/min Qn leak total 79.03 NL/min Qn average 740.6 NL/min Leak share 10.74 % Annual cost calibrated 1565 € The leak share, 10.74 %, is still twice the 5 % target of the measure Leakage above the target, which stays in the list of Leaks repaired — a third of the leaks is still a lot for a network this small. The target would take a test of under 1 s loaded in a minute.
-
Compare the scenarios
Choose Scenario → Compare scenarios.... The Figures tab has a column per scenario and the differences against the baseline. The second header row shows the state of each column: audit — current; outdated — its input has changed since; press Calculate all to bring every column up to date.
Row As is Proposed Leaks repaired Unit Source pressure 6.5 6.17 6.17 bar Source pressure, average load 6.5 6.17 6.17 bar Lowest setting without deficits 6.183 6.161 6.15 bar Demand at maximum load 1960 1708 1552 NL/min Demand at average load 995.7 899 740.6 NL/min Compressor load at maximum 78.41 68.33 62.08 % Leakage 247.4 236.9 79.03 NL/min Leakage share 25.04 26.52 10.74 % Model calibration by Audit power 0.7516 0.7516 0.7516 Annual electricity, calibrated 16.7 14.62 12.04 MWh Annual electricity cost, calibrated 2172 1900 1565 € Cost of compressed air (estimate) 2889 2528 2082 € CO2 (estimate) 8889275 7778139 6407197 g Consumers short of pressure 0 0 0 Errors and warnings 0 2 2 Saving potential of the audit measures 715.3 451.5 118.4 € The share of leaks in Proposed is higher than as is, although the leaks themselves are a little lower: the consumers take less, so the same leaks are a bigger part of what is left. Read the absolute rows, not only the shares. The two warnings of Proposed and of Leaks repaired are PG and FM with the readings of the baseline (step 5). The leak share is not among them: the warning thresholds of the leak share count only leaks drawn on the sheet, leak orifices; the leaks found by the test give the measure Leakage above the target instead.
The last row, Saving potential of the audit measures, is what the measures the audit still finds in each scenario would save: 715.3 € as is, 451.5 € after the regulator and the lower setting, 118.4 € after the repair too. What is left is mostly the rest of the leaks.
Check that Leaks repaired was made from Proposed: its tab reads Leaks repaired (6) — the four changes of Proposed and the two leak test rows — and its demand at maximum load, 1552 NL/min, is below that of Proposed. A Leaks repaired made from As is, with 6.17 typed by hand, has no R2: its tab reads (3), B2 blows its 610 NL/min again, and at 6.17 bar B1 is short of pressure (When it does not work). A setting found with the regulator in place is only safe with the regulator in place.
Three versions of one network side by side, at the same tariffs and the same measured energy. The tab Proposed (…) lists what differs from the baseline, element by element, with the measure that caused each change:
Element Change Parameter As is → Proposed Measure COMP Changed Audit pressure 6.5 → 6.17 The compressor setting can be lowered R2 Added P3 Reconnected Connected to T1, B2 → T1, R2 B2 Reconnected Connected to P3 → R2 Four rows — hence Proposed (4) on the tab. On the screenshots the elements are named by their IDs, as in lessons 7–11.
The regulator has no measure in the journal: it was placed by hand. The tab of Leaks repaired lists the same, plus the two leak test rows of COMP.
The last tab, Measures, is the journal itself: every entry of every scenario in the order it was made, with what was changed and what the measure promised at that moment. Made by the steps of this lesson, it has two entries:
Scenario Element Measure What was changed Air saved, NL/min Power saved, kW Saving a year, € Proposed ID7 - compressor The compressor setting can be lowered Audit pressure: 6.5 -> 6.17 bar 36.5 141.8 Leaks repaired ID7 - compressor The compressor setting can be lowered Audit pressure: 6.5 -> 6.17 bar 36.5 141.8 The element is named by its ID and card label. Leaks repaired has the same entry: a new scenario starts with a copy of the journal of the one it was made from. The regulator and the leak test are not there — the journal holds what Apply changed, cards replaced by hand and values set by the variant calculation, not every edit of a row. The euros are a promise: 141.8 € is what the lower setting was to save on the network with the regulator, at the moment it was applied. With two or more entries that promise a saving, a scenario ends with a bold Sum of the estimates; it is only a sum of promises, the result of them all is on Figures. Double-click an entry to go to its element in its scenario.
The screenshots of this lesson show Measures (4): in their file the card of the flow meter had been picked from the catalog again in Proposed, so Proposed has one more entry, FM_1 — Card replaced by hand — Card: VD 500 -> VD 500, and Leaks repaired copied it with the rest (there it reads FM_1 - VD 500). The columns of power and money are further right; scroll the table to see them. That is harmless (see When it does not work); a card picked again promises nothing, so there is no Sum of the estimates either.
The journal of measures: what was applied where, and what it promised. -
Work out the payback
EasyCAS gives the saving of each scenario; the price of the work comes from your supplier. Divide one by the other. With the figures of the comparison and example prices:
Measure Saving a year Investment (example) Payback Lower setting, 6.5 → 6.17 bar ≈ 142 € 0 € — a setting at once Regulator R2 before B2 ≈ 130 € 120 € with fitting ≈ 11 months Leak survey and repair 335 € 900 € 2.7 years Proposed saves 2172 − 1900 = 272 € a year, the regulator and the setting together. The journal gives the share of the setting — the 141.8 € it promised on the network with the regulator; the rest, about 130 €, is the regulator. The leak repair is the difference between the next two columns, 1900 − 1565 = 335 €. Taken in this order the savings add up to the total, As is → Leaks repaired, 606 € a year (the change column of Leaks repaired: −606.3 €). Taken separately, each against the baseline, they would not add up: the regulator and the lower setting save part of the same air.
The small plant, the small money. Two open pipes and 50 m of pipe on a 15 kW compressor working one shift give hundreds of euros, not thousands. The method is the same on a plant with forty consumers and a 160 kW room — and there the survey pays in weeks.
-
Save it
Save
lesson12.gf9. All three scenarios are kept in the one file, with the journal of measures; the comparison opens without recalculating. Lesson 13 splits the cost of the air between the departments of the plant.
When it does not work
| What you see | Why | What to do |
|---|---|---|
| Apply is greyed | The measure needs a new element or a choice the program cannot make (regulator, leak repair, control method), or it is not updated from an earlier search. | Make the change by hand in a scenario, or press Audit first. |
| The change went into the wrong scenario | Apply goes into the current scenario when it is not the baseline. | Switch with the Scenario menu before applying; undo with Ctrl+Z. |
| No The compressor setting can be lowered in the list | A consumer is short of pressure and no compressor setting cures it — it sits behind a regulator that holds its own outlet (R2 at 4 bar gives B2 3.98). Min audit pressure is then not reachable, and the measure is built from it. | Raise the regulator first: Audit set point to its Required set point, press Audit. |
| Leaks repaired shows Consumers short of pressure 1 | It was copied from a scenario without R2 — the baseline, or Proposed before step 4. Without the regulator B2 takes its 610 NL/min, and at 6.17 bar B1 gets less than 6. | Delete it (Scenario → Delete), switch to Proposed and make it again from there. |
| A column of the comparison reads outdated | Its input, or the shared Input parameters, changed after its calculation. | Press Calculate all. |
| Baseline calibration outdated on the source of a scenario | The baseline was changed after its audit: the calibration of the other scenarios is taken from it. | Switch to the baseline and press Audit, or Calculate all. |
| Power calibration of the scenarios is not 0.752 | The baseline was changed — for example its Audit pressure is no longer 6.5. The meter measured the plant at 6.5 bar; set against a baseline at another pressure it gives another K, and every scenario takes it from there. | Keep the baseline as the plant is: switch to As is, put the setting back and press Audit. Make changes only in the other scenarios. |
| Pout of a regulator takes only a few values | They are the set points of the flow curves in the card. | Type the setting into Audit set point. |
| The regulator has Audit: RegOpen | Its inlet is less than the set point plus dPmin: it opens fully and cannot hold. | Lower the set point, raise the inlet pressure, or use a regulator with a smaller dPmin. |
| Measures has Card replaced by hand with the same card on both sides (VD 500 -> VD 500) | The card of the element was picked from the catalog again in a scenario other than the baseline; every such pick is journalled. | Harmless. Ctrl+Z right after the pick takes it back. |
| A change is not on the Measures tab | The journal holds the measures applied, cards replaced by hand and values of the variant calculation. A row typed in the card or a new element is not journalled — it shows on the tab of changes. | — |
| The Undo history has gone | Switching scenarios clears it, as opening a file does. | — |
Try this next
- In Proposed, set Audit set point of R2 to
3.8. B2 is short of pressure: the required pressure decides, not the measure's advice. Set it back to 4.03. - In Compare scenarios, set Compare with to Proposed: the change columns now show what the leak repair adds on top of the setting and the regulator alone.
- Save the file as
lesson12-try.gf9. In Proposed select Undersized pipe of T1 and press Apply: T1 becomes a d-1.5 in_Equal Tee. Measures now has two entries for Proposed and the row Sum of the estimates; Leaks repaired keeps its one — it was copied before. Go on with lesson 13 fromlesson12.gf9.